Skip to main content
Contact Us

ISO 31000 Risk Matrix: Likelihood × Consequence

A practical, colour-coded 5×5 risk matrix aligned to the ISO 31000 risk management framework. Use it to prioritise risks, communicate risk levels to stakeholders, and drive treatment decisions.

5×5 Risk Matrix: Likelihood vs Consequence

ISO 31000 5×5 risk matrix showing risk ratings (Low, Medium, High, Extreme) for each combination of likelihood and consequence.
Likelihood ↓  Consequence → Insignificant Minor Moderate Major Catastrophic
Almost Certain Medium High High Extreme Extreme
Likely Medium Medium High High Extreme
Possible Low Medium Medium High High
Unlikely Low Low Medium Medium High
Rare Low Low Low Medium Medium

Risk Level Definitions

Low

Accept and monitor. No specific treatment plan required. Review during routine risk assessments.

Medium

Manage with standard controls. Assign an owner and monitor regularly. Escalate if conditions change.

High

Requires senior management attention. Develop a treatment plan with defined actions, owners, and deadlines.

Extreme

Requires immediate executive action. Halt or modify the activity until the risk is reduced to an acceptable level.

What Is an ISO 31000 Risk Matrix?

A risk matrix is a visual tool that maps the likelihood of a risk event occurring against the consequence (impact) if it does occur. The intersection of these two dimensions produces a risk rating that helps organisations prioritise which risks require immediate treatment and which can be accepted or monitored.

ISO 31000:2018 describes a six-step risk management process that includes risk identification, risk analysis, and risk evaluation. A risk matrix is one of the most widely used tools for the analysis and evaluation steps. It translates qualitative or semi-quantitative assessments into a visual format that boards, executives, and operational teams can act on.

The matrix above uses a standard 5×5 format (five likelihood levels and five consequence levels), which is the most common configuration in Australian organisations and aligns with guidance in AS ISO 31000:2018 and the international standard IEC 31010 (risk assessment techniques).

How to Build Your Risk Matrix: Step by Step

Follow these six steps to create a risk matrix calibrated to your organisation's context, as described in the ISO 31000 framework.

Define your risk criteria

Establish the criteria your organisation will use to evaluate risk significance. ISO 31000 clause 6.4 requires that criteria reflect your objectives, stakeholder expectations, and risk appetite. Document what "unacceptable" looks like before you start assessing.

Set your likelihood scale

Define five levels of likelihood with clear, measurable descriptions. Use frequency-based definitions (e.g., "Expected to occur more than once per year") rather than vague terms. See the likelihood scale table below.

Set your consequence scale

Define five levels of consequence across the impact dimensions relevant to your organisation: financial, operational, reputational, safety, regulatory. Each level should have a specific threshold, not just a label.

Map existing risks onto the matrix

For each identified risk, assess its likelihood and consequence using the scales you defined. Plot the risk in the corresponding cell. Consider both inherent risk (before controls) and residual risk (after existing controls). If the controls vocabulary is new to you, CompTIA Security+ covers the vendor-neutral foundation that maps cleanly to ISO 27001 Annex A controls.

Assign risk ratings and priorities

Each cell produces a risk rating (Low, Medium, High, Extreme). Use these ratings to prioritise treatment actions. Extreme and High risks typically require a formal treatment plan with defined owners and deadlines.

Review and update regularly

Risk is dynamic. Review your matrix quarterly at a minimum, and after any significant incident, organisational change, or regulatory update. ISO 31000 emphasises that monitoring and review runs continuously throughout the process.

Defining Your Scales

The most common reason risk matrices fail is vague scale definitions. Each level must be specific enough that two different assessors would assign the same rating to the same risk. Below are example scales that you can adapt to your organisation's context.

Likelihood Scale

Likelihood scale with five rating levels from Rare to Almost Certain, each with a measurable frequency threshold.
Level Rating Description Example Frequency
5Almost CertainExpected to occur in most circumstancesMore than once per year
4LikelyWill probably occur in most circumstancesOnce per year
3PossibleCould occur at some timeOnce every 1 to 3 years
2UnlikelyNot expected but possibleOnce every 3 to 10 years
1RareMay occur only in exceptional circumstancesLess than once in 10 years

Consequence Scale

Consequence scale with five rating levels from Insignificant to Catastrophic, with specific thresholds across financial, operational, reputational, safety, and regulatory impact dimensions.
Level Rating Financial Impact Operational Impact
5CatastrophicThreatens organisational survivalComplete loss of critical operations for >1 month
4MajorSignificant financial loss requiring board attentionMajor disruption to operations for >1 week
3ModerateMaterial financial loss manageable within budgetDisruption to some operations for >1 day
2MinorSmall financial loss absorbed within normal operationsMinor disruption, quickly resolved
1InsignificantNegligible financial impactNo meaningful operational impact

Common Risk Matrix Mistakes

A risk matrix is only as useful as the thinking behind it. Avoid these common pitfalls:

Mistake 1

Using vague scale definitions. If "Likely" means different things to different people, your risk ratings will be inconsistent. Define each level with measurable thresholds: frequencies, dollar amounts, or operational timeframes.

Mistake 2

Not calibrating to your organisation's context. A $50,000 loss is "Catastrophic" for a startup and "Insignificant" for a bank. Your consequence scale must reflect your organisation's size, risk appetite, and operating environment.

Mistake 3

Treating the matrix as the entire risk assessment. A risk matrix is one output of risk analysis, not a replacement for the full ISO 31000 process. It should be supported by risk registers, treatment plans, and monitoring activities.

Mistake 4

Not reviewing after incidents. A risk matrix is a living document. If a "Rare" event occurs, your likelihood rating was wrong. Update it. Trigger-based reviews are as important as scheduled reviews.

Mistake 5

Using a single matrix for all risk types. Cyber risks, safety risks, and financial risks may need different consequence scales. Consider domain-specific matrices that roll up into an enterprise-level view.

Resources

Continue building your risk management knowledge:

  • ISO 31000 Overview: The hub page covering ISO 31000 fundamentals and Australian adoption.
  • ISO 31000 Risk Management Guide: Deep dive into the principles, framework, and six-step process.
  • PECB ISO 31000 Risk Manager: Self-paced eLearning with exam voucher (A$409 + GST).
  • ISO 27001 Certification Guide: The information security management system that uses ISO 31000 risk methodology.
  • ControlStack: Browse ISO 27001, Essential Eight, and ISM controls alongside risk management guidance.
  • Free Resources: Download templates, checklists, and implementation guides.
  • ISO 42001 Lead Auditor: For auditors extending risk-management methodology into AI governance. AI risk categories (hallucination, bias, drift) are a 2024 to 2026 addition most auditor training hasn't covered.

Frequently Asked Questions

Common questions about ISO 31000 risk matrices.

What is a 5x5 risk matrix?

A 5×5 risk matrix is a grid that maps five levels of likelihood (Rare to Almost Certain) against five levels of consequence (Insignificant to Catastrophic) to produce 25 possible risk ratings. Each cell is classified as Low, Medium, High, or Extreme, giving organisations a visual tool to prioritise which risks need immediate treatment and which can be monitored.

How do you calculate risk in ISO 31000?

ISO 31000 does not prescribe a single formula. In practice, most organisations use Risk = Likelihood × Consequence as a starting point. The standard emphasises that risk analysis should consider the sources of risk, their positive and negative consequences, the likelihood of those consequences, existing controls, and the level of confidence in the analysis. A risk matrix is one tool for visualising the output of this analysis.

What are the 5 levels of risk?

A typical 5-level risk scale includes: (1) Low: accept and monitor, (2) Medium: manage with standard controls, (3) High: requires senior management attention and a treatment plan, (4) Extreme: requires immediate executive action, and (5) Critical: used in some frameworks for risks that threaten organisational survival. ISO 31000 does not mandate specific levels; organisations define them based on their own risk appetite and context.

What is the difference between a risk matrix and a heat map?

A risk matrix is a structured grid with defined likelihood and consequence scales used during risk analysis. A heat map is a colour-coded visual representation often used to communicate risk assessment results to stakeholders. In practice, the terms are used interchangeably, but a heat map is typically a presentation layer on top of the underlying risk matrix data.

Is a risk matrix mandatory in ISO 31000?

No. ISO 31000 is a guidelines standard, not a requirements standard, so nothing in it is mandatory. The standard describes the risk management process, including risk identification, analysis and evaluation, but does not prescribe specific tools. A risk matrix is one of the most common tools organisations use to implement the analysis and evaluation steps, but alternatives such as bow-tie analysis, Monte Carlo simulation, and fault tree analysis are equally valid.

How often should a risk matrix be reviewed?

ISO 31000 recommends that risk management be iterative and dynamic. In practice, most organisations review their risk matrix quarterly at a minimum, with additional reviews triggered by significant incidents, changes in business context, new regulatory requirements, or the completion of risk treatment actions. The review frequency should be proportionate to the rate of change in your operating environment.

Master Risk Management with ISO 31000

The PECB ISO 31000 Risk Manager credential validates your ability to build risk frameworks, facilitate risk assessments, and apply the matrix methodology in practice, from enterprise risk registers to board-level reporting.

★ 4.5/5 on Trustpilot PECB Authorised Training Partner Exam voucher + 2 attempts included